The construction of Hangzhou Asian Games venues completes 109.4% of the half-year plan, ahead of the schedule

2020-07-22 04:13:57 source: Zhang Mengyue, Shen Tingyu


Up to now, the Asian Games venues and facilities have been built at full capacity in the second quarter on the basis of the full resumption of work. By the end of June, 109.4% of the half-year plan had been fulfilled with the completion of 47.6% of the annual investment, and 57.8% of the total investment.

 

微信图片_20200715140027.jpg


Half a year has passed, what new changes have taken place in the Asian Games venues?

 

The first batch of venues (to be completed in 2020)

Highlighted: Gymnasium and Swimming Pool of Hangzhou Olympic Sports Center


微信图片_20200715140033.png


The total annual volume of work completed this quarter: 49.48%

The cumulative completed volume of work: 82.80%

 

微信图片_20200715140039.jpg


Runner-up: Wenzhou Dragon Boat Base


微信图片_20200715140043.jpg


The total annual volume of work completed this quarter: 48.89% 

The cumulative completed volume of work: 72.19%  

 

微信图片_20200715140048.jpg


Second runner-up: China·Zhejiang Ocean Sports Center


微信图片_20200715140051.jpg


The total annual volume of work completed this quarter: 36.80%

The cumulative completed volume of work: 66.23%

 

微信图片_20200715140055.png


The second batch of venues (to be completed in 2020)

Highlighted: Wenzhou Sports Center Stadium


微信图片_20200715140100.jpg


The total annual volume of work completed this quarter: 39.14%

 

微信图片_20200715140104.jpg


Runner-up: Lin'an Culture and Sports Exhibition Center


微信图片_20200715140108.jpg


The total annual volume of work completed this quarter: 38.34%

 

微信图片_20200715140111.jpg


Second runner-up: Stadium and Gymnasium of Jinhua City Sports Center


微信图片_20200715140116.jpg


The total annual volume of work completed this quarter: 37.86%

 

微信图片_20200715140120.jpg


According to the Hangzhou Asian Games Organizing Committee, the construction of Asian Games venues has reached a critical stage, and in order to ensure both the epidemic prevention and construction, all the work of venue construction will be promoted with greater strength and faster pace, and efforts will be made to complete the goals and tasks throughout the year.


(Compiled by Xu Yuhong, translated by Tao Mingzhou)

read more

12140180 The construction of Hangzhou Asian Games venues completes 109.4% of the half-year plan, ahead of the schedule public html

Up to now, the Asian Games venues and facilities have been built at full capacity in the second quarter on the basis of the full resumption of work. By the end of June, 109.4% of the half-year plan had been fulfilled with the completion of 47.6% of the annual investment, and 57.8% of the total investment.

 

微信图片_20200715140027.jpg


Half a year has passed, what new changes have taken place in the Asian Games venues?

 

The first batch of venues (to be completed in 2020)

Highlighted: Gymnasium and Swimming Pool of Hangzhou Olympic Sports Center


微信图片_20200715140033.png


The total annual volume of work completed this quarter: 49.48%

The cumulative completed volume of work: 82.80%

 

微信图片_20200715140039.jpg


Runner-up: Wenzhou Dragon Boat Base


微信图片_20200715140043.jpg


The total annual volume of work completed this quarter: 48.89% 

The cumulative completed volume of work: 72.19%  

 

微信图片_20200715140048.jpg


Second runner-up: China·Zhejiang Ocean Sports Center


微信图片_20200715140051.jpg


The total annual volume of work completed this quarter: 36.80%

The cumulative completed volume of work: 66.23%

 

微信图片_20200715140055.png


The second batch of venues (to be completed in 2020)

Highlighted: Wenzhou Sports Center Stadium


微信图片_20200715140100.jpg


The total annual volume of work completed this quarter: 39.14%

 

微信图片_20200715140104.jpg


Runner-up: Lin'an Culture and Sports Exhibition Center


微信图片_20200715140108.jpg


The total annual volume of work completed this quarter: 38.34%

 

微信图片_20200715140111.jpg


Second runner-up: Stadium and Gymnasium of Jinhua City Sports Center


微信图片_20200715140116.jpg


The total annual volume of work completed this quarter: 37.86%

 

微信图片_20200715140120.jpg


According to the Hangzhou Asian Games Organizing Committee, the construction of Asian Games venues has reached a critical stage, and in order to ensure both the epidemic prevention and construction, all the work of venue construction will be promoted with greater strength and faster pace, and efforts will be made to complete the goals and tasks throughout the year.


(Compiled by Xu Yuhong, translated by Tao Mingzhou)

]]>