2020-07-22 04:13:57 source: Zhang Mengyue, Shen Tingyu
Up to now, the Asian Games venues and facilities have been built at full capacity in the second quarter on the basis of the full resumption of work. By the end of June, 109.4% of the half-year plan had been fulfilled with the completion of 47.6% of the annual investment, and 57.8% of the total investment.
Half a year has passed, what new changes have taken place in the Asian Games venues?
The first batch of venues (to be completed in 2020)
Highlighted: Gymnasium and Swimming Pool of Hangzhou Olympic Sports Center
The total annual volume of work completed this quarter: 49.48%
The cumulative completed volume of work: 82.80%
Runner-up: Wenzhou Dragon Boat Base
The total annual volume of work completed this quarter: 48.89%
The cumulative completed volume of work: 72.19%
Second runner-up: China·Zhejiang Ocean Sports Center
The total annual volume of work completed this quarter: 36.80%
The cumulative completed volume of work: 66.23%
The second batch of venues (to be completed in 2020)
Highlighted: Wenzhou Sports Center Stadium
The total annual volume of work completed this quarter: 39.14%
Runner-up: Lin'an Culture and Sports Exhibition Center
The total annual volume of work completed this quarter: 38.34%
Second runner-up: Stadium and Gymnasium of Jinhua City Sports Center
The total annual volume of work completed this quarter: 37.86%
According to the Hangzhou Asian Games Organizing Committee, the construction of Asian Games venues has reached a critical stage, and in order to ensure both the epidemic prevention and construction, all the work of venue construction will be promoted with greater strength and faster pace, and efforts will be made to complete the goals and tasks throughout the year.
(Compiled by Xu Yuhong, translated by Tao Mingzhou)